Setting a Gradient: Drainage Falls and the Boning Rod
The drainage tile, the septic tank and the constructed wetland already published here all share a requirement none of them explains: the pipe must fall at a specific, constant gradient, and both too little and too MUCH will stop it working.
Too little and solids settle. Too much and the water runs away and leaves the solids behind — which surprises people, and is why a steep drain blocks as reliably as a flat one. The traditional figures, one in forty for a small foul drain and one in eighty for a larger one, are not arbitrary: they are the range where the flow stays fast enough to scour and slow enough to carry.
Boning rods are how that gradient gets built without an instrument in the trench. Three T-shaped rods, two set on the known ends and one carried along, and your own eye does the interpolation.
Fortgeschritten
1 day
Anweisungen
1
1
Fix the two ends before anything else
Fix the two ends before anything else
Establish the invert level — the inside bottom of the pipe — at the start and at the outfall, using the levelling method from earlier in this batch.
The outfall is usually fixed by something you do not control: an existing manhole, a ditch, a soakaway. Level it FIRST and work backwards, because discovering at the end of the trench that you needed 300 millimetres you have not got is the failure this whole rung exists to prevent.
Materialien für diesen Schritt:
Holzdübel6 StückBenötigte Werkzeuge:
Nivellierinstrument (Vermessung)
Nivellierlatte2
2
Choose the gradient, and check it against both limits
Choose the gradient, and check it against both limits
Work out the fall available over the run, and compare it with what the pipe needs. For a 100 mm foul drain, 1 in 40 is the usual figure; for 150 mm, 1 in 60 to 1 in 80.
Check BOTH ends of the range. A gradient far steeper than needed is a real fault, not a safety margin, and where the ground falls faster than the pipe should, the answer is a steep section plus a manhole or a backdrop — not a uniformly steep pipe.
3
3
Make a set of boning rods
Make a set of boning rods
Make three identical T-shaped rods — a vertical leg with a horizontal crosspiece — all exactly the same length, with the crosspieces painted a colour that stands out against soil.
Identical is the whole trick, and the only tolerance that matters is between the three: cut them together and check them against each other, not against a tape. If they differ by 10 millimetres, your trench is wrong by 10 millimetres everywhere, and nothing in the method will tell you.
Materialien für diesen Schritt:
Visierlatten3 Stück
Douglasie-Balken2 lengthBenötigte Werkzeuge:
Handsäge
Bandmaß (Rollmeter)4
4
Set sight rails at each end and bone between them
Set sight rails at each end and bone between them
Set a sight rail at each end of the run, each one exactly one boning-rod height above the intended invert at that point. The line joining the two rail tops is then parallel to the pipe, one rod height up.
Stand behind one rail and sight across both. Anyone in the trench holds the third rod on the formation: when its crosspiece lines up exactly with the two rails, the trench is at the right depth. Your eye is doing linear interpolation over thirty metres, to a few millimetres, with no instrument.
Materialien für diesen Schritt:
Douglasie-Balken4 length
Galvanisierte Nägel20 StückBenötigte Werkzeuge:
Handsäge
Klauenhammer
Nivellierinstrument (Vermessung)5
5
Lay to the invert, not to the top of the pipe
Lay to the invert, not to the top of the pipe
Bed each pipe so that the INSIDE BOTTOM sits on the line, and check every single one before backfilling.
Pipes vary in wall thickness, so laying to the top of the barrel puts a step in the invert at each joint — and a step is where solids catch. Support the barrel along its length, never on the collars, and never pack it up on a stone: a pipe bearing on two hard points cracks under backfill.
Benötigte Werkzeuge:
Visierlatten
Wasserwaage6
6
Why too steep blocks a drain
Why too steep blocks a drain
Jupyter-Notebook wird geladen …
7
7
Prove it with water before you backfill
Prove it with water before you backfill
Run a bucket of water down the finished pipe and watch it at the outfall. It should arrive promptly and completely, leaving nothing standing.
Water is the only test that matters, it costs a bucket, and it is available exactly once — after backfilling, finding a reverse fall means digging the whole run out again. Put a spirit level in the trench along the pipe as a second check: at 1 in 40 the bubble should sit visibly but only slightly off centre, and a bubble that looks central means the fall is not there.
Benötigte Werkzeuge:
WasserwaageMaterialien
4- 6 StückPlatzhalter
- 3 StückPlatzhalter
- 4 lengthPlatzhalter
- 20 StückPlatzhalter
Benötigte Werkzeuge
7- Platzhalter
- Platzhalter
- Platzhalter
- 1 vendor sell this, none ship to you yetPlatzhalter
- Platzhalter
- Platzhalter
- Platzhalter
Verwandte Blueprints
Diese Blueprints teilen Wissen — Techniken, Materialien oder Prinzipien
CC0 Gemeinfrei
Dieser Blueprint ist unter CC0 veröffentlicht. Sie dürfen dieses Werk für jeden Zweck frei kopieren, ändern, verbreiten und verwenden, ohne um Erlaubnis zu fragen.
Unterstützen Sie den Maker, indem Sie Produkte über seinen Blueprint kaufen, wo er eine Maker-Provision von Anbietern festgelegt, verdient. Oder erstellen Sie eine neue Iteration dieses Blueprints und verbinden Sie ihn in Ihrem eigenen Blueprint, um Einnahmen zu teilen.