Setting Out a Building: Profiles and Batter Boards
Emma

作成者

Emma

23. 9月 2026SE
22
0
0
0
0

Setting Out a Building: Profiles and Batter Boards

You have pegged out a perfect rectangle. Now the digger arrives and removes every peg in the first ten minutes, because the pegs are exactly where the trench goes. The answer is older than machinery and completely reliable: move the information OFF the building line. Batter boards — profiles — are horizontal rails set well outside the excavation, carrying saw-cuts or nails that mark where each line runs. Stretch a string between two matching marks and the line reappears, exactly where it was, as many times as you need it. This rung is the one that turns a survey into a building, and it is the one most often improvised badly. It also carries the levels: the top of the board is usually set to a round height above datum, so a tape from the string gives depth without re-levelling.
中級者
1 day

手順

1

Set the profiles well clear of the dig

Drive two stout posts at each corner region, at least a metre and a half outside the building line, and nail a horizontal rail across them. A metre and a half is a minimum, not a target — an excavator's tracks and its spoil heap need more than people expect, and a profile knocked out of position is worse than no profile, because it still looks authoritative. Put them where the machine will not go, and brace them so a knock moves the whole assembly rather than twisting one post.

このステップの材料:

ダグラスファーの梁ダグラスファーの梁8 length
亜鉛めっき釘亜鉛めっき釘50 個

必要な工具:

釘抜き付き金づち釘抜き付き金づち
手のこぎり手のこぎり
2

Set every rail to ONE level

Using the water level or the optical level, set the top edge of every rail to the same height — ideally a round number above your datum, such as exactly one metre. Now a single tape measurement down from a string gives you the depth of anything, anywhere on the site, with no arithmetic. Setting the rails at arbitrary heights works for the plan lines and throws away this entire second function, which is most of what profiles are worth.

必要な工具:

オートレベル(測量)オートレベル(測量)
標尺標尺
透明ビニールチューブ透明ビニールチューブ
3

Transfer the lines onto the rails

Stretch a string along each building line from its corner pegs, extend it to the rails, and mark where it crosses with a saw-cut — not a pencil mark. A saw-cut survives rain, mud, gloves and three months. A pencil line does not last a week outdoors. Cut a second mark for the outside of the foundation and a third for the trench edge, and label each one on the rail in paint or with a nailed tag, because by the time you need them you will not remember which is which.

このステップの材料:

墨壺の糸(水糸)墨壺の糸(水糸)100 metre
亜鉛めっき釘亜鉛めっき釘30 個

必要な工具:

手のこぎり手のこぎり
下げ振り下げ振り
4

Check the diagonals again, from the profiles

String up all four building lines from the rails and measure the diagonals of the rectangle they form. This checks the transfer, not the original layout — a saw-cut in the wrong place is easy and invisible. The diagonal check costs two minutes and catches it before anything is dug. Re-check the diagonals every time you re-string, for the whole life of the job, because a rail does get knocked eventually and nothing about a wrong string looks wrong.

必要な工具:

メジャー(巻尺)メジャー(巻尺)
5

Working depths and the tolerance you actually have

Jupyter ノートブックを読み込み中…

必要な工具:

メジャー(巻尺)メジャー(巻尺)
6

Leave a record on the site itself

Paint the datum height and the rail height on one post, and note them in the book with a sketch showing which corner is which. Sites change hands, work stops for winter, and the person who returns may not be you. A profile with no stated level is a piece of wood. Two painted numbers turn it back into a survey, and they cost thirty seconds at the moment you still remember what they are.

材料

3

必要な工具

7

CC0 パブリックドメイン

このブループリントはCC0で公開されています。許可を求めずに、自由にコピー、修正、配布、あらゆる目的で使用できます。

メイカーを応援するには、ブループリント経由で製品を購入してください。メイカーには メイカーコミッション がベンダーにより設定されています。または、このブループリントの新しいイテレーションを作成し、自分のブループリントにコネクションとして含めて収益を共有できます。

ディスカッション

(0)

ログイン してディスカッションに参加

コメントを読み込み中...