Setting a Gradient: Drainage Falls and the Boning Rod
The drainage tile, the septic tank and the constructed wetland already published here all share a requirement none of them explains: the pipe must fall at a specific, constant gradient, and both too little and too MUCH will stop it working.
Too little and solids settle. Too much and the water runs away and leaves the solids behind — which surprises people, and is why a steep drain blocks as reliably as a flat one. The traditional figures, one in forty for a small foul drain and one in eighty for a larger one, are not arbitrary: they are the range where the flow stays fast enough to scour and slow enough to carry.
Boning rods are how that gradient gets built without an instrument in the trench. Three T-shaped rods, two set on the known ends and one carried along, and your own eye does the interpolation.
Àárín
1 day
Ìlànà
1
1
Fix the two ends before anything else
Fix the two ends before anything else
Establish the invert level — the inside bottom of the pipe — at the start and at the outfall, using the levelling method from earlier in this batch.
The outfall is usually fixed by something you do not control: an existing manhole, a ditch, a soakaway. Level it FIRST and work backwards, because discovering at the end of the trench that you needed 300 millimetres you have not got is the failure this whole rung exists to prevent.
Àwọn ohun èlò fún ìgbésẹ̀ yìí:
Àwọn èèkàn igi6 ẹyọÀwọn irinṣẹ́ tí a nílò:
Ẹ̀rọ ìwọ̀n ìtẹ́lẹ̀ (ìwọ̀n ilẹ̀)
Ọ̀pá ìwọ̀n ìtẹ́lẹ̀2
2
Choose the gradient, and check it against both limits
Choose the gradient, and check it against both limits
Work out the fall available over the run, and compare it with what the pipe needs. For a 100 mm foul drain, 1 in 40 is the usual figure; for 150 mm, 1 in 60 to 1 in 80.
Check BOTH ends of the range. A gradient far steeper than needed is a real fault, not a safety margin, and where the ground falls faster than the pipe should, the answer is a steep section plus a manhole or a backdrop — not a uniformly steep pipe.
3
3
Make a set of boning rods
Make a set of boning rods
Make three identical T-shaped rods — a vertical leg with a horizontal crosspiece — all exactly the same length, with the crosspieces painted a colour that stands out against soil.
Identical is the whole trick, and the only tolerance that matters is between the three: cut them together and check them against each other, not against a tape. If they differ by 10 millimetres, your trench is wrong by 10 millimetres everywhere, and nothing in the method will tell you.
Àwọn ohun èlò fún ìgbésẹ̀ yìí:
Àwọn ọ̀pá ìwòye ìdàgbà3 ẹyọ
Ìtì igi Douglas fir2 lengthÀwọn irinṣẹ́ tí a nílò:
Ayùn Ọwọ́
Okùn Ìdíwọ̀n4
4
Set sight rails at each end and bone between them
Set sight rails at each end and bone between them
Set a sight rail at each end of the run, each one exactly one boning-rod height above the intended invert at that point. The line joining the two rail tops is then parallel to the pipe, one rod height up.
Stand behind one rail and sight across both. Anyone in the trench holds the third rod on the formation: when its crosspiece lines up exactly with the two rails, the trench is at the right depth. Your eye is doing linear interpolation over thirty metres, to a few millimetres, with no instrument.
Àwọn ohun èlò fún ìgbésẹ̀ yìí:
Ìtì igi Douglas fir4 length
Ìṣó tí a bò pẹ̀lú sínkì20 ẹyọÀwọn irinṣẹ́ tí a nílò:
Ayùn Ọwọ́
Òòlù oníkànnì
Ẹ̀rọ ìwọ̀n ìtẹ́lẹ̀ (ìwọ̀n ilẹ̀)5
5
Lay to the invert, not to the top of the pipe
Lay to the invert, not to the top of the pipe
Bed each pipe so that the INSIDE BOTTOM sits on the line, and check every single one before backfilling.
Pipes vary in wall thickness, so laying to the top of the barrel puts a step in the invert at each joint — and a step is where solids catch. Support the barrel along its length, never on the collars, and never pack it up on a stone: a pipe bearing on two hard points cracks under backfill.
Àwọn irinṣẹ́ tí a nílò:
Àwọn ọ̀pá ìwòye ìdàgbà
Ìwọ̀n Ìtẹ́jú6
6
Why too steep blocks a drain
Why too steep blocks a drain
Ń ṣí ìwé Jupyter…
7
7
Prove it with water before you backfill
Prove it with water before you backfill
Run a bucket of water down the finished pipe and watch it at the outfall. It should arrive promptly and completely, leaving nothing standing.
Water is the only test that matters, it costs a bucket, and it is available exactly once — after backfilling, finding a reverse fall means digging the whole run out again. Put a spirit level in the trench along the pipe as a second check: at 1 in 40 the bubble should sit visibly but only slightly off centre, and a bubble that looks central means the fall is not there.
Àwọn irinṣẹ́ tí a nílò:
Ìwọ̀n Ìtẹ́júÀwọn ohun-èlò
4- 6 ẹyọÀyè
- Àyè
- 4 lengthÀyè
- 20 ẹyọÀyè
Àwọn irinṣẹ́ tó nílò
7- Àyè
- 1 vendor sell this, none ship to you yetÀyè
- Àyè
Blueprint tó jọra
Àwọn blueprint wọ̀nyí pín ìmọ̀ — ọ̀nà, ohun-èlò tàbí ìlànà
CC0 Àgbègbè Gbogbogbò
Blueprint yìí ti jáde lábẹ́ CC0. O lè ṣe àdàkọ, yí padà, pín, àti lò láìsí ìyọ̀ǹda.
Ṣàtìlẹ́yìn Olùṣẹ́dá nípa rírà àwọn ọjà nipasẹ̀ Blueprint wọn Ẹ̀san Olùṣẹ́dá tí àwọn Olùtajà gbé kalẹ̀, tàbí ṣẹ̀dá àtúnṣe tuntun ti Blueprint yìí kí o sì fi sínú Blueprint rẹ gẹ́gẹ́ bí ìsopọ̀ láti pín owó-wíwọlé.